Progress Report

Nokomis Waterfront

  • Updated: October 22, 2025
  • Developer / GC: P.A.M. Construction
  • Location: Nokomis, FL

Current Status

The Nokomis waterfront project continues to progress on schedule, with the structure now transitioning from the masonry phase to the dry-in stage. All major load-bearing elements are complete, and the roof framing system is in place. The crew has maintained consistent productivity and organization, with no notable delays or safety issues reported on site.

    Work Completed to Date

    Foundation & Structural Slab

    • Concrete foundation, footers, and main slab have been completed and passed inspection.

    • Perimeter grading and drainage preparation were finalized before vertical construction.

    Masonry & Structural Shell

    • Both first and second-floor CMU walls have been erected and tied in with structural beams.

    • Lintel pours and tie-beams completed for all window and door openings.

    • Rough window and door openings have been properly framed and verified for consistency with architectural plans.

    Roof Framing

    • Full truss package installed and braced across the second level.

    • Plywood roof decking material staged and ready for installation.

    • Crew is currently finalizing alignment, hurricane straps, and hold-downs before sheathing begins.

    Site Organization

    • Jobsite remains clean and efficiently staged.

    • Construction trailer and waste container on site; regular cleanup schedule being maintained.

    • No active erosion or access issues present.


    Upcoming Work

    The following milestones are scheduled for the next two weeks:

    • Roof sheathing installation and dry-in.

    • Window and exterior door installation.

    • Rough-in for mechanical, electrical, and plumbing (MEP).

    • Exterior waterproofing and stucco prep.

    Once the structure is watertight, interior framing and system layouts will begin concurrently.


    Summary

    This build has successfully reached the framing milestone, marking approximately 40–45% total completion. The project remains within budget and projected timeline. The waterfront location and quality of construction continue to align with high-end custom home standards in the surrounding area.

    Related Projects

    Service Title

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam

    Service Title

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam

    Service Title

    Lorem ipsum dolor sit amet, consectetur adipiscing elit. Phasell sed nibh dignissim, cursus tellus sit amet, ultrices mauris. Aliquam